- Two kinds of commercial inspection
- What a property condition assessment includes
- What drives the cost of a commercial inspection
- What a baseline PCA leaves out
- Lender rules that dictate when and how you inspect
- City inspection fees for commercial projects
- Worked example: inspection costs on a restaurant build-out
- Commercial inspection vs. residential home inspection
- How to get comparable PCA quotes
- Common mistakes
- Related guides
A commercial building inspection has two very different price tags. City inspections on a commercial permit are paid through the permit, with extra charges only for reinspections (about $71 to $195 per visit in the schedules below) and after-hours work ($100 to $292 an hour). A private property condition assessment (PCA), the inspection buyers and lenders order before a purchase or loan, is quoted per property by engineering and consulting firms; there is no public price schedule, so the cost depends on building size, number of systems, report scope, and deadline. Get at least three quotes against the same written scope.
If you are planning a build-out rather than a purchase, the building permit cost calculator includes a commercial tenant improvement option.
Two kinds of commercial inspection
Due diligence inspection (PCA). A walk-through survey plus document review that tells a buyer or lender what condition the property is in and what it will cost to fix. Voluntary, but nearly always required by commercial lenders.
Permit inspection. The building department's inspections of permitted construction, such as a tenant improvement, roof replacement, or new building, at foundation, rough-in, framing, and final stages. Mandatory whenever a permit is pulled.
What a property condition assessment includes
ASTM E2018, the Standard Guide for Property Condition Assessments, sets the baseline. The current edition, E2018-24, describes a PCA performed "by performing a walk-through survey and conducting research," with the goal "to identify and communicate material physical deficiencies." A typical scope covers:
- Site: paving, drainage, landscaping, site lighting, retaining walls
- Structure and envelope: foundation, framing, facade, windows, roofing
- Mechanical, electrical, and plumbing systems: age, condition, remaining useful life
- Vertical transportation: elevators and escalators
- Life safety and fire protection: sprinklers, alarms, egress, at a screening level
- Interior finishes and common areas
- Document review: permits, certificates of occupancy, open code violations, prior reports
- Interviews with the owner, property manager, and building department where possible
The deliverable is a Property Condition Report that "includes opinions of costs for suggested remedies," usually split into immediate repairs and a reserve table of replacements over the hold or loan term. The standard is explicitly "not intended to be construed as technically exhaustive," and it includes abbreviated accessibility screenings rather than full ADA audits.
What drives the cost of a commercial inspection
Because PCA fees are quoted, knowing the cost drivers helps you compare bids:
- Building size and count. A single small retail building is a one-person, one-day site visit. A multi-building apartment complex or campus takes a team.
- Property type. ASTM's annex covers multifamily, office, and retail. Hotels, hospitals, labs, and industrial buildings with process equipment take more specialist time.
- System complexity. Central plants, elevators, generators, and fire pumps each add review.
- Report format. Lender-specific formats, such as Fannie Mae's Form 4099 template or HUD's CNA e-Tool, require specific tables and cost schedules.
- Specialist add-ons. Roof cores, infrared scans, full accessibility surveys, seismic risk assessments, and destructive testing are outside a baseline PCA.
- Deadline. Rush turnaround inside a short due diligence period often costs more.
- Access and travel. Remote sites and limited tenant access add time.
What a baseline PCA leaves out
Budget separately for any of these you need, because each is its own scope and fee:
- Phase I environmental site assessment, for contamination risk
- Seismic risk assessment, common for lenders in high-seismic regions
- Full accessibility audit, rather than the abbreviated screening in the ASTM appendices
- Roof cores, infrared moisture scans, or facade drops for detailed envelope findings
- Mold, asbestos, or lead sampling
- Elevator or fire protection testing by licensed specialty contractors
- Zoning report confirming legal use, parking, and setbacks
Lender rules that dictate when and how you inspect
If you are financing multifamily property, the lender's guide decides how fresh the report must be:
| Lender program | PCA requirement | Timing rule |
|---|---|---|
| Fannie Mae Multifamily | PCA for each property, complying with Form 4099 | Up to 12 months old with a site visit within 90 days; under 6 months if the report includes the high-performance building module |
| Freddie Mac Multifamily | Property condition (engineering) report noting deviations from the latest ASTM E2018 | Dated within 6 months of the full underwriting package; site inspection within 30 days before the report date |
| HUD MAP (FHA multifamily) | Capital needs assessment meeting at least ASTM E2018-15, prepared in HUD's CNA e-Tool | New CNA at intervals of no more than 10 years for insured properties |
Sources: Fannie Mae Multifamily Guide, Section 404, Freddie Mac Multifamily Guide, Chapter 62, HUD MAP Guide.
Two practical consequences. First, order the PCA early enough that it is still valid at closing; a report that ages out means paying for an update. Second, Fannie Mae will not deliver a loan on a property with a condition rating of 4 or 5, so serious findings can change the deal, not just the price.
Freddie Mac also classifies repairs into critical repairs, priority repairs to be completed within 365 days, and a shorter 90-day category, which your loan documents will hold you to.
City inspection fees for commercial projects
On a commercial permit, inspections come with the permit fee, but commercial projects often need extra visits and off-hours work because occupied buildings cannot always shut down.
| Jurisdiction | Commercial reinspection / extra visit | After-hours | Other |
|---|---|---|---|
| Austin, TX (eff. Oct. 1, 2026) | $70.98 | $141.95/hr | Commercial pre-demolition inspection $169.88 |
| Miami-Dade County, FL (eff. Oct. 1, 2026) | $94.88 per extra inspection | $142.33/hr regular day; $237.21/hr holiday, 4-hr min | 50% permit fee reduction when a private provider does review and inspection |
| Denver, CO | $100/hr | Prepaid, 2-hr min | Same hourly rate for non-customary inspections |
| Seattle, WA (eff. Jan. 1, 2026) | $146 | $292/hr | Hourly rate $292 for other services |
| Phoenix, AZ (eff. Jan. 20, 2026) | $195 | $195/hr, $390–$585 min | Miscellaneous inspection $195/hr |
Sources: Austin commercial fees, Miami-Dade IO 4-63, Denver development fees, Seattle 2026 Fee Subtitle, Phoenix fee schedule.
Structural special inspections on new commercial buildings, such as concrete testing and steel welding inspection, are performed by agencies the owner hires and are billed separately from the city's fees.
Worked example: inspection costs on a restaurant build-out
A tenant is building out a 3,000 sq ft restaurant in an occupied Austin shopping center. The landlord requires noisy work and inspections to happen after hours.
- Two after-hours inspections at $141.95 an hour, one hour each: $283.90
- One commercial reinspection after a failed above-ceiling inspection: $70.98
- Inspection extras: $354.88, on top of the permit, plan review, and separate health department approvals
The same pattern in Phoenix would cost at least $390 for each after-hours request plus $195 for the reinspection, or $975, showing how much the local schedule matters. Ask the landlord early whether daytime inspections are allowed; a single change in the work letter can remove most of these charges.
Free · Printable checklist
Know which projects need a permit — before you start
A one-page checklist of common home projects, typical permit and inspection fee ranges, and the inspection sequence most cities follow.
- Which projects usually need a permit (and which don’t)
- Typical permit and inspection fee ranges
- The inspection order: rough-in to final
- Questions to ask your building department
Unlocked — the Home Project Permit Checklist is ready.
Open the Home Project Permit ChecklistCommercial inspection vs. residential home inspection
| Commercial PCA | Residential home inspection | |
|---|---|---|
| Standard | ASTM E2018 | State standards of practice |
| Typical inspector | Engineering or consulting firm, often with licensed engineers | Licensed home inspector |
| Output | Property condition report with cost tables and reserve schedule | Narrative report with photos and recommendations |
| Who orders it | Buyer, lender, or both | Buyer |
| Price | Quoted per property | Published price lists by square footage are common |
See house inspection fees for residential pricing.
How to get comparable PCA quotes
- Write the scope. State the ASTM edition, the lender format, the number of buildings, the reserve term (for example, 12 years), and any add-ons.
- Provide documents up front. Rent roll, prior reports, capital expenditure history, and permits shorten the site visit.
- Confirm the site visit date against the lender's timing rule.
- Ask who signs the report and whether a licensed engineer reviews it.
- Separate the Phase I environmental report, which is a different scope.
Common mistakes
Ordering the minimum scope for a complex building. A baseline PCA screens systems; a building with an aging central plant or elevator may need a specialist review before you commit.
Letting the report expire. Freddie Mac's six-month and 30-day rules leave little slack in a slow closing.
Confusing condition with code compliance. A PCA notes open violations it finds in records, but it is not a code inspection.
Ignoring lease responsibilities. In net-leased properties, the tenant may own roof or HVAC replacements; read the leases before you underwrite reserves.
Related guides
Planning work on the building after closing? Read the construction permit cost guide and the building inspection cost guide. For electrical findings, see electrical inspection costs. All guides are in the permit and inspection cost hub.
Lender requirements and city fees change. Use this guide for planning and confirm requirements with your lender and building department.
Frequently asked questions
What standard governs a commercial building inspection?
How old can a property condition report be for a multifamily loan?
Is a city commercial inspection the same as a PCA?
Does a PCA include an environmental assessment?
- commercial building inspection cost
- commercial property inspection
- building inspection
- due diligence
- commercial real estate
Informational only
This guide explains general rules as published by the IRS and other official sources. It is not tax, legal, or investment advice, and it can’t account for your full situation. How we research and update guides.